Construction Meetings and Schedule

Meetings:

Have all subs verify existing systems before we shut down their systems and have them sign off and take pictures for protection.

Whenever the owner has another contractor on the job site, you need to get a certificate of insurance from that contractor showing our company as additionally insured.

Schedule:

Address long lead-time items immediately, i.e., create a log and review weekly.

Remember, we can legally get an extension of time if you are delayed by lack of information or direction. We cannot legally get you paid for a delay without a written notification at the time of the delay.