Hiring an elevator sub

Tuesday, August 7th, 2012

When you hire an elevator sub DO NOT let them begin without a signed unaltered subcontract.

"Who you know"

Tuesday, July 10th, 2012

When I first got in this business I thought it was “who you know” now atoledo.com I know you must have command of your business as a professional first and then it becomes “who you know.”

If you ever encounter any environmental issues

Wednesday, May 9th, 2012

If you ever encounter any environmental issues stop immediately! Advise the owner/architect about these issues and the most important advice you can give, if asked, is online casinos to say, if we do not report such an incident to the authorities it is a criminal offense by those involved.

Environmental Issue

Thursday, July 7th, 2011

If you ever encounter any environmental issues stop immediately! Advise the owner/architect about these issues and the most important advice you can give, if asked, is to say, if we do not report such an incident to the authorities it is a criminal offense by those involved.

Trade contractor's owner and contract obligations

Monday, April 18th, 2011

The trade contractor’s owner is usually a pretty talented person and is probably making more than we are so treat him with respect. Even though you may think because However, the truth is that there are plenty of players who don’t take the time to study blackjack online tips. you are the general contractor and running a major job that you can abuse people. Just make him perform per his contract obligations and be respectful.

Project Meeting Minutes

Monday, April 4th, 2011

Project meeting minutes should be like a diary. It tells the complete story with clarity so someone who does not understand construction can understand it even three years later in court. If you have to explain what it means then you have failed with your minutes.

Internal Operational Highlights

Friday, February 25th, 2011

It is a contractual requirement that you must notify the owner/architect/subcontractor immediately of any delays that you intend to claim at the time of the delay. We cannot file craps for a claim at the end of the project for something that happened in the beginning of the project unless you notified the owner at the actual time it happened.

Bonds

Wednesday, February 9th, 2011

"Punch List" Items

Monday, January 31st, 2011

For some reason the owner only remembers the last thing we did – which is usually the “punch list” items – so do it ae mobile game right and efficiently to secure future work from the customer. The last 1% of the project is the 90% the owner remembers about us.

Change Orders and Pricing

Monday, January 24th, 2011

Be sure to address extension of time and money on all change orders.

When you get a change order always give the owner a “guesstimate” for the dollar amount even if you need a day to get back to him. Never take more than two weeks to have the final price. We price out whole buildings in two weeks, so let’s get it done.